Vijay reports the following information regarding its production costs. Compute its production cost per unit under absorption costing.


Answer:

Per unit costs                   Absorption costing
Direct material                         $10
Direct labor                              $20
Variable overhead                    $10
Fixed overhead                        $8
Total product cost per units     $48



Compute its production cost per unit under variable costing.

Answer:
Per unit costs
Direct material                         $10
Direct labor                              $20
Variable overhead                    $10
Fixed overhead                           -
Total product cost per units     $40